Project List (All Priority Planing Projects)


Sr No. Executive Agencies Funding Agencies Project Type Project Name Status Start Date End Date (%) Remarks
1 N.H. Division PWD Ayodhya Ministry of Road Transport and
Highways
Road Projects Improvement and Upgradation of 84 Kosi Parikrama
Marg (NH-227 B) Package - 4&6
Planning - - 0 % 1) Package- 4 (From km73.300 (Bikapur) to km
140.960 (Patranga) (Total length- 67.660 Km,
Total Project Cost-1679.75) This work is
sanctioned by the Ministry on 07.11.2022, Tender
invited by the Ministry and Financial bid opened
on 23.07.2024. LOA issued on 21.11.2024 Under
land acquisition, 3D published on 18.03.2024. 69
villages 3G completed,1 village 3G under
progress. Payment through Bhumi Rashi Portal in
progress. Disbursement amount Rs. 310 .00 Cr.
Possession of 90% land given by CALA. Agreement
formation in process. (2) Package- 6 (From km
160.200 (Bahuvan Madar Majha) to km 224.040
(Jagarnathpur) (Total length- 63.84 Km Total
Project Cost-2008.70) This work is sanctioned by
the Ministry on 22.05.2023. Tender invited by
the Ministry and Financial bid opened on
23.07.2024. LOA issued on 09.12.2024 Under land
acquisition 3D Published on 02-02-2024. 37
villages 3G completed. 1 village 3G in process.
3 villages 3D under progress and remaining 1
village 3A under progress. Disbursement amount Rs.
331.00 Cr. Possession of 80% land given by CALA.
Agreement formation in process.
2 N.H. Division PWD Lucknow Ministry of Road Transport and
Highways
Road Projects Improvement and Upgradation of 84 Kosi Parikrama
Marg (NH-227 B) Package-5
Planning - - 0 % 1) Package- 5(From km 140+960 (Patranga) to Design
Km 160+200 (Bahuvan Madar Majha) (Total length-
19.240 Km, Total Project Cost-1192.33 Cr.) This
work is sanctioned by the Ministry on
16.03.2023 Tender invited by the Ministry on
dated 01.09.2023 and financial bid were opened on
06.08.2024 Under land acquisition, Barabanki
district: LA required: 97.5532 Ha.
(Govt.-21.8806& Pvt.- 75.6726 ha- 18 villages).
3G completed – 75.6726 hec. (18 villages) 3G
balance – Nil Awarded amount - Rs.83.65 Cr.
Disbursed amount - Rs.63.736 Cr. (76.19%).
Balance- Rs.19.91 Cr.

Possession letter of 18 Villages of District
Barabanki received from SLAO Office. Gonda
district: LA required: 10.0909 Ha.. (Govt.-.6302
& Pvt.-9.4607 ha- 01 villages). 3G completed –
9.4607 hec. (01 villages) Awarded amount -
Rs.13.67 Cr. Disbursed amount -Rs.10.85 Cr.
(79.36 %). Balance- Rs. 2.82 Cr. Possession
letter of 01 Villages of District Gonda received
from SLAO Office. LOA to be issued by Ministry of
Road Transport & Highway.

3 National Highway Division,
PWD, Basti
Ministry of Road Transport and
Highways
Road Projects Improvement and Upgradation of Chaurasi Kosi
Parikrama Marg (NH 227 B) Package - 1
Planning - - %

1) Package-1(From km 228.920 (Jagarnathpur) to
km 235.960/0.000 (Makhauda dham) to km 29.000
(sarpur)) (Total length- 36.04, Total Project
Cost-912.50)- This work has been started from
28.05.2025. Under-land acquisition 3D notified on
09.03.2023 and Award for 53 villages out of 53
village declared till date & Physical
Possession of 48 villages received. 2) Package-
2(From km 29.000 (Sarpur) to km 47.800 (Gosaiganj)
(Total length- 18.878, Total Project Cost- 1031.96
Cr.): - This work is sanctioned by the Ministry on
15.02.2023. In this part, a bridge of more than 3
km length is proposed over the Saryu River. Tender
invited on 19.06.2023. Under-land acquisition-
Award for 15 villages out of 15 village declared
and Disbursement is in progress. 3) Package-3
(From km 47.800 (Gosaiganj) to km 73.300 (Bikapur)
(Total length- 25.500, Total Project Cost-587.97)
-This work has been started from 19.05.2025,
Under-land acquisition- Award for 27 villages out
of 27 village declared & Physical Possession
of 26 villages received.

4 Uttar Pradesh Tourism Uttar Pradesh Tourism Tourism Tourist Facilitation Centre Planning - - %

Tourism Department to invite tender
applications


कार्यदायी संस्था:Central Public Works Department (CPWD)

गातिमान परियोजना नाम:Construction of 100 Bedded MCH Hospital at IMS BHU Varanasi

कार्य आरंभ करने की तिथि कार्य पूर्ण करने की तिथि परियोजना लागत (रू0 लाख में) पुनरीक्षित लागत (रू0 लाख में) क्रमिक अवमुक्त धनराशि (रू0 लाख में) क्रमिक व्यय (रू0 लाख में) परियोजना क्रमिक भौतिकप्रगति (प्रतिशत में)
15-04-2018 31-08-2020 4550 0 3620 3650 100
Last Meeting Instruction
28-09-2020 सर सुन्दर लाल चिकित्सालय बी0एच0यू में 100 शैयायुक्त मेटर्निंटी विंग की प्रगति 100.00 प्रतिशत है। अवगत कराया गया कि बिल्डिंग तैयार है तथा साफ सफाई का कार्य चल रहा है, किन्तु आपरेशनल करने के लिये मेडिकल इक्यूपमेंट और बेड व एक्स-रे इत्यादि की व्यवस्था बी0एच0यू0 को करना है जिस हेतु बी0एच0यू0 द्वारा आवश्यक कार्यवाही की जा रही है।
Issues
28-09-2020 सर सुन्दर लाल चिकित्सालय बी0एच0यू में 100 शैयायुक्त मेटर्निंटी विंग की प्रगति 100.00 प्रतिशत है। अवगत कराया गया कि बिल्डिंग तैयार है तथा साफ सफाई का कार्य चल रहा है, किन्तु आपरेशनल करने के लिये मेडिकल इक्यूपमेंट और बेड व एक्स-रे इत्यादि की व्यवस्था बी0एच0यू0 को करना है जिस हेतु बी0एच0यू0 द्वारा आवश्यक कार्यवाही की जा रही है।

Company
  • Home
  • Contact Us
Follow Us

Stay tuned for the Upcoming events & News

Address

© 2025 Ayodhya Development Authority, Program Management Unit, Ayodhya All Rights Reserved

©2025Ayodhya Development Authority, Program Management Unit, Ayodhya All Rights Reserved